![]() ![]() Since more resources will work on remaining activities of the project, it is expected to finish the project on time. Extra resources are planned and extra budget is allocated to accommodate the increasing costs. The third step is crashing the project.This is one of the advantages of fast tracking in project management over crashing because fast-tracking does not bring an extra cost to project. Remaining critical path activities are evaluated and possible activities that can be performed in parallel can be done to shorten the duration of the project. If re-estimation results in a later deadline for project completion, Fast-tracking the project must be considered.Re-estimation will show how long will it take to complete remaining activities of the project. Because, for the remaining activities, if the risks that were considered during planning are no longer valid, re-estimation of the remaining activities can result in shorter activity durations. If a project is behind the schedule, there are 5 major steps that must be followed in sequence. However, since these extra resources were not in the initial plan, there will be an additional cost if crashing is used for schedule compression.ĥ major steps to follow if the project is behind the schedule This will help to complete the project faster. Because if it is possible to assign more than one resource on an activity, activity duration will decrease respectively. If the scope is the same and project is behind schedule, another option for compressing the schedule is putting extra resources on remaining activities of the project. In crashing schedule compression technique, there is a trade-off between cost and schedule. The 2nd schedule compression technique: What is crashing in project management? This is called fast tracking schedule compression approach. If you are aiming to finish the project faster, you can perform Activity #2 and Activity #3 in parallel after completing activity #1. As a fast tracking example, let’s consider that there are 3 activities that need to be completed each other: Activity #1, Activity #2 and Activity #3. Let’s visualize fast tracking over a sample. If critical path activities are depending on each other because of resource dependency or if there is a discretionary dependency, you can fast track those activities to complete remaining activities faster. For instance, you cannot start testing of a screen before completing development. Because, if two activities are depending on each other by nature, you cannot do these two activities in parallel. ![]() This is possible only the activities are not in mandatory dependency. I n fast tracking schedule compression technique, critical path activities are performed in parallel instead of series. Let’s give fast tracking project management definition. The 1st schedule compression technique: What is fast tracking in project management?įirst approach is Fast Tracking. Let’s go over each schedule compression approach one-by-one. There are 2 approaches for schedule compression according to project management certification courses. Because, if a project scope has not changed, and if the project is behind schedule, you can meet the planned deadline only by compressing the remaining schedule of the project. The objective of schedule compression is to try to compress the schedule without changing project scope. Schedule compression techniques are applied during develop schedule process if a project is behind the schedule. There are two methods for schedule compression, so we are also going to review what is crashing in project management and fast tracking project management definition. In this article, we are going to see schedule compression definition. In order to meet the project deadline, you need to take corrective actions to get back on track and these are called schedule compression methods.Īttend our 100% Online & Self-Paced One-Hour Free PMP Training.Īs explained in the PMI certification training, schedule compression helps you to get your project back on track. In terms of schedule, the actual durations of tasks can take longer than planned. No matter how well you plan a project, actual results will differ from what you have planned.
0 Comments
Leave a Reply. |
AuthorWrite something about yourself. No need to be fancy, just an overview. ArchivesCategories |